15 – 20 mm |
| |
|
|
Form a slope to the top of the feature band to enable water run
off to occur and to create a weatherproof joint.
Create the raised band feature 1. as a single
application and depending on the depth required,
this may need to be built up in 2 layers with the 2nd
layer being formed onto the still wet 1st layer.
The raised feature must be completed prior to the
application of the main render 2. The support
structure can be created using timber or other
temporary formwork. |
Raised string band |
|
15 – 20 mm in one layer
depending on finish |
|
| Note: The same application principles are applied for the creation of string
courses, key stones and plinths. For additional guidance contact Parex. |
|
|
|