Ideally a stop bead should be
used here to provide a quality
finish and to enable a sealant
to be applied. Ensure the DPC
projects past the face of the
render.
To assist against stress
fractures in the blockwork,
embed a layer of TV10 mesh
within the render, to the
underside of the cill a
minimum of 300 mm deep.
We would recommend two
layers of bed joint
reinforcement should be
applied within the blockwork
directly above openings to
resist possible stress cracking
at the corners of the openings.
Refer to item 10 in the General
Guidance and Specification
section. |
Cill Detail |
|
|
|
|
|